Stage 3 Construction Progress Print

Activity

Linear Feet Completed

% Complete

Bridge Deck
Removal
percentage_bar_100
7,415 LF
100%


Grid Deck
Installation
percentage_bar_100
7,415 LF
100%


Concrete Bridge
Deck Poured
percentage_bar_85
6,415 of 7,415 LF
86.5%


Hatem-Bridge-Progress-Rendering-2010-06-29
View a photo illustration of the construction progress. pdf