Stage 3 Construction Progress
Activity
Linear Feet Completed
% Complete
Bridge Deck
Removal
7,415 LF
100%
Grid Deck
Installation
7,415 LF
100%
Concrete Bridge
Deck Poured
6,415 of 7,415 LF
86.5%
View a photo illustration of the construction progress.